DCMA 14 Point Check – Hard Constraints

This is an extension to our previous article regarding the DCMA 14 Point Check. The following method was used for Primavera P6 version 6.1, there was no other schedule analytical tool available so we developed a work around approach.

First open Primavera P6 and the project you wish to analyse.

 

We now need to add the Total Activities column.

 

Make a note of the Total Activities in the schedule.

Now we need to create a new report using the Report Wizard.

 

Select Activities as it is activity data we require in the report.

 

Select Columns

 

Add Primary Constraint as we are looking to find out how many Hard Constraints are against the Project.

 

Select Filter and create a filter to show only the Hard Constraints.

 

 

Click Next.

 

Type in the report name.

 

Click Run Report.

 

As we want the report in Excel select ASCII and ensure that the Text Qualifier is set to “.

 

The report will open in Microsoft Excel, highlight the Activity ID’s and make a note of the count.

In this example there are no Hard Constraints the calculation to work out the threshold is as follows:

Hard Constraints Check = (0/1749) *100 = 0%. The DCMA has set a threshold of no more than 5% for Hard Constraints, in this example this project meets this criteria.

There are a further 13 checks prescribed by the DCMA which along with the Hard Constraints Check that will be detailed out in further supporting documentation and video tutorials at http://www.myxacom.com where knowledge is no weight to carry.LinkedIn_PCS_Group_2

myxacom.com Crowdfunding Project

LinkedIn_PCS_Group_2

We are launching a Crowdfunding project at the end of September 2016 to raise funds for development of the myxacom.com website. The funds will be used to:

  • Enhance the site for members
  • Upgrade of recording and studio equipment
  • Development of interactive e-learning
  • Initial funding for a recording studio

Over the next few weeks we will be developing the project to tell our story and creating reward packages for backers.

We will be posting regular updates here to keep you all informed as to our progress with the project.

If you are interested in helping us fund the future development of the site please email me at michael.higgins@xacom.co.uk.

 

DCMA 14 Point Check – Critical Path Test

LinkedIn_PCS_Group_1This is an extension to our previous article regarding the DCMA 14 Point Check. The following method was used for Primavera P6 version 6.1, there was no other schedule analytical tool available so we developed a work around approach.

Open up the project for analysis in Primavera P6.

 

Select a critical activity that sits towards the front end of the critical path.

Extend this activity by a large quantity.

Schedule the project.

Analyse if the end date changes on the project.

In this example the end date changes which demonstrates that the Critical Path is working. This means that this project meets the DCMA criteria.

There are a further 13 checks prescribed by the DCMA which along with the Critical Path Test Check that will be detailed out in further supporting documentation and video tutorials at http://www.myxacom.com where knowledge is no weight to carry.

DCMA 14 Point Check – Finish Start Relationship

LinkedIn_PCS_Group_1This is an extension to our previous article regarding the DCMA 14 Point Check. The following method was used for Primavera P6 version 6.1, there was no other schedule analytical tool available so we developed a work around approach.

First open the project that is to be checked then we need to create a new report through the Report Wizard.

 

As it is the relationships we are interested in here, select Activity Relationships in the Subject Area.

We do not require any additional subject areas so click next.

 

Click on Columns so we can select the appropriate data we wish to include in the report. In this case we are interested in the Relationship Type. Only include this in the Selected options column.

 

Name the Report.

“As we want the report in Excel select ASCII and ensure that the Text Qualifier is set to “.

 

The report will run.

 

Delete the top two rows.

Add a 1 next to each identified Relationship Type.

 

Now insert a pivot table to summarise the data into the relevant Relationship Types.

Now divide each total for each Relationship Type by the total for all Relationship Types. In this example that will be 1693/1869.

 

In this example the FS relationships make up over 90% of the total Relationship types on the project. The DCMA criteria states that FS relationships should be no less than 90% – therefor this project meets this criteria.

There are a further 13 checks prescribed by the DCMA which along with the Finish Start Relationships Check that will be detailed out in further supporting documentation and video tutorials at http://www.myxacom.com where knowledge is no weight to carry.