DCMA 14 Point Check – Critical Path Length Index

LinkedIn_PCS_Group_2

This is an extension to our previous article regarding the DCMA 14 Point Check. The following method was used for Primavera P6 version 6.1, there was no other schedule analytical tool available so we developed a work around approach.

Open the required project for analysis in Primavera P6.

Make a note of the Total Float – in this example it’s 0.

 

Select Group & Sort.

Select None in the grouping.

 

Now select Filter.

Filter in Critical activities only.

 

Go back into Grouping & Sort and select show grand totals.

 

The Duration for the Critical Path is shown, document this down.

 

Now we have the data we can apply the formula, so in the example used in this document this would look like:

Critical Path Length Index = (1293 – 0)/1293 = 1.

There are a further 13 checks prescribed by the DCMA which along with the CPLI Check that will be detailed out in further supporting documentation and video tutorials at http://www.myxacom.com where knowledge is no weight to carry.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑

%d bloggers like this: